Projects We Have Worked On
Select milestone projects handled by Directors of ARCEP Engineering Ltd while in the employ of NEPA/PHCN/TCN
- Management of National Grid Expansion (330KV & 132KV) Network (2003-2012)
- Distribution Network Development Projects in Abuja & Lagos Zones and nationwide (1999-2003)
- Electricity Grid Telecommunications Projects (Several) (1999-2012)
- Grid development Projects at 330/132/33KV Levels (Construction of several Substations & Transmission Lines) (2002-2008)
- National Grid Islanding System Project (2006)
- Lagos Distribution System Expansion (LDSE) – Substations & Transmission Lines ( at 132KV & 33KV Levels) (1985-1990)
- Kano-Dutse-Azare 132KV D/C & S/C Transmission Lines with associated Substations at Dutse & Azare (2001-2007)
- Rerouting of Ikeja West-Ayede 330KV & Papalanto-Abeokuta 132KV S/C Transmission Lines at Owiwi Dam & Water Works Project Site, Ogun State (2006-2009)
- Installation & Commissioning of 2nd 90MVA 330/132/13.8KV Transformer & Associated Switchgears at Birnin Kebbi (2006)